Verna Lee Roadway came under increased traffic due to the construction of Harker Heights High School at the intersection of Verna Lee and FM 2410. The City’s Thoroughfare Plan identified this roadway as a major collector.

The existing roadway was an eighteen foot wide ribbon asphalt section with open ditches. The improved section was increased to a forty-eight foot wide curb and gutter street with curb inlets and storm drain culverts. The street section was designed to handle the increased loading from the many school buses and other commercial vehicles.

 
     
 